Today was all over the place. Main objective: Trim work. Chris and I worked a lot today on the richlite trim work but we paused separated and worked on other projects throughout the day. The wall got insulation, the redwood was finished, and the gabions were on a production line. Every bit was moving. After a while the electrician Brent showed up and we discussed various things as he buttoned up what was left. We were all in the cabin taking a vote on the loft when all of the sudden three electrical inspectors were walking around having one of the most difficult discussions I had ever been witness to. After all of the options were discussed and the inspectors left we juiced the house. Lights were on and outlets worked. It was a fast and rewarding day.